The ten-minute Chicago lot screen

A broker sends a PIN and wants an answer by Friday; the architect is free in two weeks. This screen takes ten minutes, with the ordinance already read.

By RealDevelop · Published · updated

The bottleneck is the analysis, not the land

For a Chicago parcel, what a site permits is spread across the base district’s bulk table, the use tables, overlay districts, transit-served-location rules, parking standards and whatever amendments landed since the last printing. Doing it properly by hand takes a day; doing it for forty candidate sites takes a month you don’t have, so most sites get screened on a guess.

The screen below takes the reading out of the critical path. The ordinance is already read, so there are no regulatory parameters to type and nothing to get wrong. The times are what the product takes live today: options generate in seconds and the report builds in two or three.

Five steps, 10 minutes

  1. 1

    Paste the PIN or address 1 min

    Lot lines, dimensions, district and overlays load from county and City records. Nothing to type.

  2. 2

    Read what the ordinance already says 2 min

    District bulk standards, TOD tier and parking relief, ARO trigger, PD threshold, blocked uses, per-edge setbacks. Each figure cited to Title 17.

  3. 3

    Generate the options 3 min

    Every typology that fits the lot and the ordinance, often ten to twenty variants, ranked against your brief. The top three open first; any one lands on your lot in 3D with units and parking by level.

  4. 4

    Decide go, visit or no-go 2 min

    Save the options you would build as scenarios and compare them side by side. Then read each row of the matrix below against the one you would build, and write the call down with its reason and the citations.

  5. 5

    Send the pre-diligence report 2 min

    The cited read plus the option you chose, as a PDF for a partner or lender before diligence money is spent. Not a PZR-grade zoning report, and not an architect’s brief.

About 10 minutes from the broker’s PIN to a documented decision.

Fig 1 Step 3: options ranked inside the envelope; the top three shown, nine explored on this lot.

Step 4: the Go / Visit / No-Go matrix

The checks hold the facts; the matrix is the decision. Read each row against the option you would build. The conditions are advice, the citations are facts, and the decision stays yours.

CriterionGoVisitNo-Go
Units vs your targetWithin 10% under lot-area-per-unit and FARReachable only with TOD relief or an assemblageMore than 20% short by right
UsePermitted by right in the districtSpecial use or conditionalResidential blocked (M districts, PMD)
Height and FAR headroomFits with marginFits only at max; stepbacks bite the top floorsNeeds a map amendment
ParkingRatio met on site, or TOD reduction appliesNeeds a reduction the alderman must supportCannot be met without losing units
Affordable requirementUnder the ARO trigger, or priced inAt the trigger; model on-site vs in-lieuNot modelled
Planned DevelopmentBelow PD thresholdsAt a threshold; one design change avoids itTriggers PD review
AccessAlley or curb cut presentAlley only; loading unresolvedNo legal access

After the screen

A go is the start of the deal, not the end of the work. Frame the brief with the architect (about an hour): lot and context, zoning of record, your target units and stalls, the option that fits, the flags, and what still needs a human. Attach it to the offer (about 30 minutes): the massing on the actual lot, the programme summary and the compliance checks with citations. Then diligence to closing: the seven manual-diligence items and the City’s zoning letter, requested early.

In Chicago, if the lot needs a rezoning or a planned development, add the aldermanic read: aldermanic prerogative makes community input a gating item for rezonings.

What this is not

Not a zoning opinion letter, not an architect’s stamp, not a pro forma, not a build promise. The screen is for deciding what to pursue. A desk analysis cannot see recorded easements, prior variations and administrative adjustments, planned-development ordinances that supersede base zoning, or a map amendment filed last week. Confirm before you commit.