Guide · Chicago
Chicago lot qualification checklist
Six questions that decide whether a Chicago lot is worth a visit: transit status, the ARO, PD thresholds, alley and corner, blocked uses and per-edge setbacks.
A broker sends a PIN. Before an architect, a consultant or a site visit, six questions decide whether the lot is worth the next dollar. Each one below says what to check, where the answer sits in Title 17 and what the Go / Visit / No-Go matrix row says. The matrix is advice; the citations are facts.
1 Is the lot transit-served?
What to check
Whether the parcel is within 2,640 ft of a CTA or Metra rail station entrance, or within 1,320 ft of a CTA bus-line corridor segment on the enumerated list. Distance is measured to the parcel, and not every bus route qualifies. Transit status carries parking relief by right; the bulk bonuses are a different matter and need an approval route.
Where it is in Title 17
§17-3-0402-B, §17-10-0102-B and Table 17-17-0400-B define the locations. §17-10-0102-B.1(a) allows the residential parking minimum to be cut by up to 100% by right outside D districts. The bulk bonuses need a Type 1 map amendment (§17-13-0302), a planned development (§17-13-0600) or a project covered by the ARO through an entitlement.
What the matrix row says
Parking row. Go: ratio met on site, or the TOD reduction applies. Visit: needs a reduction the alderman must support. No-Go: cannot be met without losing units. In transit-served -3 districts, putting 50, 75 or 100% of the ARO requirement on site steps FAR from 3.0 to 3.5, 3.75 or 4.0 (§17-3-0403-B) and lot area per unit from 400 to 350, 325 or 300 sq ft (§17-3-0402-B). At least 50% on site also adds 5 ft to every band of the transit height table (§17-3-0408-B).
2 Does the ARO apply?
What to check
Whether the project is covered by the Affordable Requirements Ordinance. Coverage is defined in Municipal Code Chapter 2-44, outside the zoning title, and Title 17 only hooks into that definition. Check coverage there; this guide quotes no thresholds because they change. In a community-preservation area, Title 17 also limits which building types a transit-served lot may add.
Where it is in Title 17
Chapter 2-44 (§2-44-085) defines coverage. §17-2-0303-B.3 and §17-2-0303-B.4 prohibit new detached houses in RT and RM districts and new two-flats in RM districts in those areas; §17-3-0307.2 covers B and C districts. §17-10-0102-B.4 lets freed parking floor area be replaced one to one with on-site affordable floor area.
What the matrix row says
Affordable requirement row. Go: under the ARO trigger, or priced in. Visit: at the trigger; model on-site against in-lieu. No-Go: not modelled. A deal that has not priced the requirement has not been screened.
3 Does it trip a planned-development threshold?
What to check
Whether the project is large enough to need planned-development review, and whether the parcel already sits inside a planned development, in which case that PD ordinance governs rather than the base district. Check the mandatory thresholds in Chapter 17-8 (the 17-8-0500 thresholds) against your lot area and floor area; this guide quotes none of them. The D districts and RM-6 and RM-6.5 set no maximum height, so planned-development review governs tall buildings there.
Where it is in Title 17
Chapter 17-8 holds the thresholds. §17-4-0407 states there is no maximum building height in the D districts, and §17-2-0311-A sets none for RM-6 and RM-6.5.
What the matrix row says
Planned Development row. Go: below PD thresholds. Visit: at a threshold; one design change avoids it. No-Go: triggers PD review.
4 Alley and corner: how does the lot get in?
What to check
Alley access, curb cuts, and whether the curb cut you need can be permitted. A corner lot has two street edges and each is judged on its own; read the districts on each side, because Chicago setbacks are contextual. This is practice rather than a rule quoted from the ordinance: use it to decide what to walk on the visit.
Where it is in Title 17
The setback ranges are in §17-2-0305 to §17-2-0309 and §17-3-0404 to §17-3-0406. Access is a site fact the ordinance sections do not settle; confirm it on foot and with the City.
What the matrix row says
Access row. Go: alley or curb cut present. Visit: alley only, loading unresolved. No-Go: no legal access.
5 Is the use blocked?
What to check
Whether household living is allowed at all. Residential is not permitted in the M districts, and new housing there needs a zoning map amendment first; household living is not a general use in them. There is no household living in C3, and no coach-house or conversion-unit entry in the D and M use tables. Ground-floor dwelling units are generally not permitted in the B and C districts.
Where it is in Title 17
§17-5-0207 (M districts), §17-3-0207 (C3) and §17-4-0207 (D districts) are the use tables.
What the matrix row says
Use row. Go: permitted by right in the district. Visit: special use or conditional. No-Go: residential blocked (M districts, PMD). A blocked use is the cheapest no on the list; check it first on any M-district lot.
6 What do the per-edge setbacks leave?
What to check
Front, side and rear setbacks on each edge of the lot, then what footprint remains. On a standard lot this is usually what binds. The figures the screen shows are marked verified when read from the ordinance table and approximation when derived from a contextual formula; treat an approximation as a number to confirm per lot, as with the RT-4 scalars on the developers page.
Where it is in Title 17
§17-2-0305 to §17-2-0309 for residential districts and §17-3-0404 to §17-3-0406 for B and C districts.
What the matrix row says
Height and FAR headroom row. Go: fits with margin. Visit: fits only at max; stepbacks bite the top floors. No-Go: needs a map amendment.
The bulk basics
- Density: lot area divided by minimum lot area per unit, rounded down (§17-2-0303-A, §17-3-0402-A).
- Floor area: lot area times FAR (§17-2-0304-A, §17-3-0403-A).
- Height: read from the district table (§17-2-0311-A, §17-3-0408-A, §17-4-0407).
- Parking: required spaces consume the same lot the building wants (§17-10-0102, §17-10-0207-C).
What this is not
Not a zoning opinion letter, not an architect’s stamp, not a pro forma, not a build promise. A desk analysis cannot see recorded easements, prior variations and administrative adjustments, planned-development ordinances that supersede base zoning, or a map amendment filed last week. Confirm before you commit.
Report vs the City’s zoning letter · The ten-minute lot screen
Checklist questions
How close to transit does a lot have to be?
Within 2,640 feet (half a mile) of a CTA or Metra rail station entrance or exit, or within 1,320 feet (a quarter mile) of a CTA bus-line corridor roadway segment listed in Table 17-17-0400-B (§17-3-0402-B, §17-10-0102-B). Distance is measured to the parcel, and the bus-corridor list is a specific enumerated table, so not every bus route qualifies.
Do the transit bulk bonuses apply by right?
No. The bulk bonuses require an approval vehicle: a Type 1 zoning map amendment (§17-13-0302), a planned development (§17-13-0600), or a project already covered by the ARO through an entitlement as defined in §2-44-085, and the project must include at least one affordable unit on site. Only the parking reductions operate by right.
Does transit status change what I can build?
Substantially, and it is the most commonly missed factor. A transit-served location can carry reduced parking minimums plus floor area, height and density bonuses. Whether a parcel qualifies depends on its distance to a qualifying station or corridor, so it has to be resolved per parcel rather than per district.
Can I build housing on an M-district lot?
Residential is not permitted in the M districts, and new housing needs a zoning map amendment first (§17-5-0207). Household living is not a general use in them.